    As I understand 10-606 and 10-614, the bonding bushing and bonding jumper is only required where a metal service conduit enters the service equipment.

    There is a sketch in the Code Handbook that illustrates this.

    I believe that the original intent was to supplement the bonding afforded by concentric knockouts in the enclosure.

    Ed

  2. #2
    Inactive Member alitt001's Avatar
    Join Date
    June 30th, 2004
    Posts
    13
    Follows
    0
    Following
    0
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    Quoted
    0 Post(s)

    Post

    An unfused service conduit would only need a ground busing on one end right? What if it has an emt coupling in it?

  3. #3
    Inactive Member twh's Avatar
    Join Date
    April 3rd, 2002
    Posts
    93
    Follows
    0
    Following
    0
    Mentioned
    0 Post(s)
    Tagged
    0 Thread(s)
    Quoted
    0 Post(s)

    Post

    On one end - right, even if it has a coupling.

    A bond bushing is also required on the supply side conduit, if it enters the meter or splitter through a knock-out.